5. Jonathan and Victoria can finish a job in 13 days. Jonathan can do the job himself in 26 days. if Victoria wanted to do the job alone, how long would it
take her?
6. If a certain job can be finished by 18 workers in 26 days. How many workers
are needed to finish job in 12 days?
.
7. A group of 40 workers can finish digging a tunnel in 12 days. how many
workers can finish the job in 8 days?


5. Jonathan and Victoria can finish a job in 13 days. Jonathan can do the job

himself in 26 days.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
What is the length of the unknown leg in the right triangle ?
Answers: 2
question
Mathematics, 21.06.2019 17:30
Mickey needs to cut pieces of ribbon that are each 1 meter long tie onto balloons. if he has 8 pieces of ribbon that are each 1 dekameter long. how many 1 meter pieces of ribbon can he cut
Answers: 1
question
Mathematics, 21.06.2019 22:00
The customer price index(cpi), which measures the cost of a typical package of customer goods,was 208.8 in 2011 and 244.1 in 2016.let x=11 corresponding to the year 2011 an estimate to cpi into 2013 and 2014. assume that the data can be modeled by a straight line and the trend to continue idenfinitely.use data points to find such a line and then estimate the requested quantities
Answers: 1
question
Mathematics, 21.06.2019 22:30
The given diagram shows the parts of a right triangle with an altitude to the hypotenuse. using the two given  measures, find the other four.
Answers: 1
You know the right answer?
5. Jonathan and Victoria can finish a job in 13 days. Jonathan can do the job himself in 26 days. i...
Questions
Questions on the website: 13722363