If 4 electricians can wire some new houses in 20 days, how many electricians would be required to do the job in 10 days? a. 30
b. 8
c. 45
d. 2

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
Does anyone know how to do geometryme with this problem
Answers: 1
question
Mathematics, 21.06.2019 19:00
The distributive property allows you to say that 3(x − 1) = 3x −
Answers: 1
question
Mathematics, 21.06.2019 21:30
Taylor wants to paint his rectangular deck that is 41 feet long and 24 feet wide. a gallon of paint covers about 350 square feet. how many gallons of paint will taylor need to cover the entire deck? round your answers to two decimal places when necessary.
Answers: 1
question
Mathematics, 21.06.2019 23:40
Will give brainliest b. describe the function over each part of its domain. state whether it is constant, increasing, or decreasing, and state the slope over each part.
Answers: 1
You know the right answer?
If 4 electricians can wire some new houses in 20 days, how many electricians would be required to do...
Questions
question
Mathematics, 02.12.2021 20:00
question
Health, 02.12.2021 20:00
question
Spanish, 02.12.2021 20:00
Questions on the website: 13722359