At 13000 direct labor hours, the flexible budget for indirect materials is $26000. if $28400 are incurred at 13400 direct labor hours, the flexible budget report should show the following difference for indirect materials:

$2400 favorable.
$2400 unfavorable.
$1600 favorable.
$1600 unfavorable.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 19:10
The development price itself is such a huge barrier, it's just a very different business model than boeing's used to. our huge development programs are typically centered around commercial airplanes, military aircraft, where there is a lot of orders. and right now the foundation of the business is two bites a year.
Answers: 3
question
Business, 21.06.2019 20:30
The distinction between a normal and an inferior good is
Answers: 3
question
Business, 22.06.2019 07:40
The cutting department of cassel company has the following production and cost data for july. production costs 1. transferred out 12,300 units. beginning work in process $0 2. started 3,900 units that are 60% materials 62,856 complete as to conversion labor 12,622 costs and 100% complete as manufacturing overhead 23,100 to materials at july 31. materials are entered at the beginning of the process. conversion costs are incurred uniformly during the process. determine the equivalent units of production for (1) materials and (2) conversion costs. materials conversion costs total equivalent units of production link to text link to text compute unit costs. (round unit costs to 2 decimal places, e.g. 2.25.) materials $ conversion costs $ link to text link to text prepare a cost reconciliation schedule. (round unit costs to 2 decimal places, e.g. 2.25 and final answers to 0 decimal places, e.g. 1,225.) cost reconciliation costs accounted for transferred out $ work in process, july 31 materials $ conversion costs total costs $
Answers: 1
question
Business, 22.06.2019 08:30
What is the key to success in integrating both lethal and nonlethal activities during planning? including stakeholders once a comprehensive operational approach has been determined knowing the commander's decision making processes and "touch points" including stakeholders from the very beginning of the design and planning process including the liaison officers (lnos) in all the decision points?
Answers: 1
You know the right answer?
At 13000 direct labor hours, the flexible budget for indirect materials is $26000. if $28400 are inc...
Questions
question
Mathematics, 24.09.2019 20:00
question
Biology, 24.09.2019 20:00
Questions on the website: 13722367