Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $42,200; design $556,000; and construction oversight $124,200. The cost drivers and estimated use are as follows.

Activities Cost Drivers Expected Use of Cost Driver/Activity
Initial concept formation Number of project changes 15
Design Square feet 138,000
Construction oversight Number of months 105

Compute the predetermined overhead rate for each activity.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 19:30
Oz makes lion food out of giraffe and gazelle meat. giraffe meat has 18 grams of protein and 36 grams of fat per pound, while gazelle meat has 36 grams of protein and 18 grams of fat per pound. a batch of lion food must contain at least "46,800" grams of protein and 70,200 grams of fat. giraffe meat costs $1/pound and gazelle meat costs $2/pound. how many pounds of each should go into each batch of lion food in order to minimize costs? hint [see example 2.]
Answers: 1
question
Business, 22.06.2019 19:30
The usa today reports that the average expenditure on valentine's day is $100.89. do male and female consumers differ in the amounts they spend? the average expenditure in a sample survey of 47 male consumers was $135.67, and the average expenditure in a sample survey of 38 female consumers was $68.64. based on past surveys, the standard deviation for male consumers is assumed to be $34, and the standard deviation for female consumers is assumed to be $17.
Answers: 1
question
Business, 22.06.2019 23:00
Draw a flowchart for a process of interest to you, such as a quick oil-change service, a factory process you might have worked in, ordering a pizza, renting a car or truck, buying products on the internet, or applying for an automobile loan. identify the points where something (people, information) waits for service or is held in work-in-process inventory, the estimated time to accomplish each activity in the process, and the total flow time. evaluate how well the process worked and what might be done to improve it.
Answers: 2
question
Business, 22.06.2019 23:10
Powell company began the 2018 accounting period with $40,000 cash, $86,000 inventory, $60,000 common stock, and $66,000 retained earnings. during 2018, powell experienced the following events: sold merchandise costing $58,000 for $99,500 on account to prentise furniture store. delivered the goods to prentise under terms fob destination. freight costs were $900 cash. received returned goods from prentise. the goods cost powell $4,000 and were sold to prentise for $5,900. granted prentise a $3,000 allowance for damaged goods that prentise agreed to keep. collected partial payment of $81,000 cash from accounts receivable. required record the events in a statements model shown below. prepare an income statement, a balance sheet, and a statement of cash flows. why would prentise agree to keep the damaged goods?
Answers: 2
You know the right answer?
Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity h...
Questions
Questions on the website: 13722359